You can change the inside of your condo unit, but not on your own say-so. Your management corporation (MCST) sets the renovation rules, and the Building and Construction Authority (BCA) says structural slabs, beams, columns and walls can't be altered without a Professional Engineer's assessment and the Commissioner of Building Control's approval. Windows and external walls need your MCST's approval too.
So before you hire anyone, get your estate's renovation guidelines and the approved plans of your unit. Between them they show which walls are structural, when the work can run and what the management will ask your contractor for. If you'd rather have one firm visit and measure, do the trade work with its specialists and supervise it through to handover, that's what our condo renovation service is for. Where the work needs an engineer, we arrange one.
This guide takes the questions in the order you'll meet them: what's yours to change, what to collect from the estate, who approves what, how each trade works in a condo, the order of works, what drives the cost, new versus resale, and how to brief a contractor. The step-by-step on the MCST application itself is in our article on condo renovation approval and MCST rules.
What you can change in a condo, and who decides
Inside your unit, the finishes are yours to change. The structure, the outside of the building and anything shared with other units belong to everyone, and that's where approvals come in.
Owning a condo unit makes you a subsidiary proprietor, and automatically part of the management corporation (MCST). The by-laws it passes bind you even if you weren't at the meeting that voted them in.
The line between yours and shared is drawn on the strata title plan. Generally, everything inside a lot belongs to the owner, and areas outside it are usually common property. Some things inside your unit are common property anyway: any structural element of the building, pipes, wires, cables or ducts used by two or more units, and the waterproof membrane on an external wall or roof. BCA counts even the external walls of your unit as common property.
The floor slab is shared too, but not its top layers. BCA's summary of the changes gazetted in 2018 says slabs, excluding the underlayment, became common property, along with fire sprinklers and central air-conditioning systems. The flooring finish and the underlayment on top of the slab aren't shared.
HDB issues the renovation permits for HDB flats, while condo units are managed by their own MCST, which sets the renovation rules, and government agencies such as BCA and the Urban Redevelopment Authority (URA) come in where the work touches structure, windows, wiring or floor area.
That's why two condos side by side can have different working hours, deposits and drawing requirements. The national rules are the same, but each estate writes its own by-laws and guidelines. The table sums up who has a say over each part of your unit.
Who has a say over each part of a condo unit, from BCA's strata guides and URA's renovation guidelines
Scroll across to compare all columns →
| Part of the home | Whose it is | Who has a say before work starts |
|---|---|---|
| Floor and wall finishes, carpentry, fittings inside the unit | Yours | Your MCST, through its by-laws and renovation guidelines |
| Walls that aren't structural | Yours | Your MCST, which may ask for a Professional Engineer's endorsement, as BCA's 2014 advisory suggested to estates |
| Structural walls, slabs, beams and columns | Common property | Your MCST, plus a Professional Engineer's assessment and the Commissioner of Building Control's approval |
| Windows and external walls | External walls are common property; you maintain external openable windows | Your MCST and any relevant government agency; window works by an approved window contractor or registered builder |
| Pipes, cables and ducts serving two or more units | Common property | Your MCST |
| Open-sided covers over a balcony, private enclosed space or roof terrace | Yours to propose | Your MCST's consent, plus BCA's and the fire safety authority's requirements where they apply; no URA planning permission |
| Anything adding floor area, such as roofing a private enclosed space | Yours to propose | A 90% resolution of the MCST, and URA and BCA approval where needed |
Get these from your estate before you plan
Start at the management office, before any design work. Ask for the renovation guidelines, the application form and the by-laws. Your MCST makes the by-laws, and under the strata law changes gazetted in November 2018 it has to display the full set on its notice board and let you view them at the management office for free, with a copy available for a prescribed fee.
For the approved plans of your unit, BCA sells copies through its Plan Purchase Application Form, and the strata title plan, which shows where your unit ends and common property begins, can be obtained from the Singapore Land Authority at a cost. BCA has also advised MCSTs to keep a full set of approved structural plans that you can use to plan your renovation, so ask the management office first.
Check your Sale and Purchase Agreement as well. BCA tells you to check with the developer or the MCST and the Sale and Purchase Agreement about renovation restrictions before carrying out any work.
What the estate's guidelines settle
Hours, deposits and protection are estate rules, so expect them to differ from one condo to the next. Home & Decor's 2026 ownership guide describes MCSTs enforcing strict working hours, security deposits and rules on common areas. The National Environment Agency (NEA) regulates noise from additions and alterations (A&A) works in landed homes, and for a condo unit NEA sends residents to the estate's MCST, so your estate's by-laws and guidelines set the working hours.
Read the guidelines for these before you agree a start date or a quote:
- Working days and hours. When noisy work such as hacking and drilling can run, and whether quieter work has longer hours.
- The deposit. How much it is, what the management deducts it for, and what it checks before returning it.
- Lift and corridor protection. Which lift your contractor uses, how it and the common corridor must be covered, and who checks it.
- Deliveries and debris. Where lorries load, when materials move through the estate, and how hacked debris leaves.
- Drawings and documents. Whether the application needs a layout plan, a Professional Engineer's endorsement or details of the electrical and window works.
Note
If a figure for hours or the deposit comes from another estate, a forum or a contractor, treat it as theirs. Only your own estate's guidelines bind your renovation.
Which works need approval, and from whom
BCA's own guidance says building works in strata-titled developments, such as condominiums, might require MCST's approval, and your by-laws and guidelines say which. The government approvals sit on top of that for particular kinds of work.
The approvals, work by work
- Work inside the estate. Your MCST, where its by-laws and renovation guidelines ask for approval. In BCA's words, such works might require the MCST's approval.
- Changes that may affect how the building looks. BCA's strata guide says you should apply to your MCST for improvements or additions which may affect the appearance of any building.
- Structural walls, slabs, beams or columns. Your MCST, because they're common property, plus a Professional Engineer's assessment and the Commissioner of Building Control's approval. BCA's 2014 advisory to estates restates that all demolition works involving structural elements require plan to be approved with a permit to start, and supervision by a Qualified Person, meaning a registered architect or Professional Engineer.
- Non-structural walls. Your estate may ask for a Professional Engineer's endorsement on the plans, as BCA's 2014 advisory suggested to estates.
- Extra floor area or splitting the unit. URA planning permission. Internal works do not require planning permission when there is no increase in floor area and the unit still works as one self-sufficient home. Extra floor area also needs a 90% resolution of the MCST.
- Wiring and power points. The Energy Market Authority's (EMA) rules decide who may do the work (see the electrical part below).
- Windows. Your MCST's approval, and BCA's rules on who may install them.
Who applies, and what happens without approval
In short, your MCST's by-laws and guidelines say which works it has to approve, BCA comes in for structure and windows, URA for extra floor area or splitting a unit, and EMA's licensing rules decide who may touch your wiring.
The application is yours as the owner: BCA's advisory to MCSTs refers to renovation plans submitted by subsidiary proprietors, which is the legal term for unit owners, so it goes in under your name, with the drawings and any engineer's endorsement your estate asks for.
If improvements were made to a unit without the approval the strata law requires, the MCST may serve a notice requiring the owner at the time to put them right at their own cost, and if they don't, it may do the work and recover the cost. That owner may not be the one who did the work, which matters when you buy resale. Separately, BCA says that if you're found with unauthorised building additions and/or alterations, you'll have committed an offence under the Building Control Act.
The application itself, with the documents estates commonly ask for, is covered step by step in our article on MCST approval for condo renovation.
What each trade involves in a condo
The work itself is the same trade work as anywhere else. What changes in a condo is who has to sign off, what's shared with your neighbours, and what the estate lets your contractor do in the common areas.
Hacking and wall removal
Structural slabs, beams, columns and walls can't be altered without proper assessment by a Professional Engineer, and approval from the Commissioner of Building Control is also required.
For walls that aren't structural, BCA's 2014 advisory tells MCSTs that renovation plans should be endorsed by a civil or structural Professional Engineer certifying that no structural works are involved, for any demolition other than floor tiles, before they approve it. It is advice to estates, so yours may or may not ask for it. The same advisory asks that such demolition be done by contractors with trained workers certified by BCA Academy, and that work stops and a Professional Engineer is called in whenever the structural reinforcement bars are exposed.
A plastered wall doesn't show whether it's structural. That's why the Professional Engineer checks the approved structural plan and inspects the unit before signing. For walls that aren't structural, see our hacking and demolition service, and for wider additions and alterations, our A&A works page.
Watch out
Never let anyone start knocking on a wall to "see if it's hollow". Until a Professional Engineer has checked the approved plans, treat every wall as possibly structural.
Flooring, overlay or hack
Overlay lays the new floor over your existing tiles; hacking removes them first. BCA's advisory leaves the hacking of floor tiles out of its Professional Engineer endorsement, but your estate's guidelines may still need approval for the noisy work, and they set its hours.
Overlay saves the noise and debris, but it raises the floor. Check the main door, which opens onto the common corridor, every internal door and the step into the bathroom against the new height before you choose. Our flooring guide explains which floors suit an overlay, and our article on whether overlay or hacking costs less once doors and damp are counted works through the trade-offs. For the work itself, see our flooring service.
Painting
Inside walls and ceilings are yours to repaint. The outside face of the building isn't, because external walls are common property, so leave facade-facing walls to the MCST and check how your estate treats balcony walls. Our painting service covers interior and whole-unit repainting.
Electrical work and the licensed electrical worker
The Electricity Act 2001 makes it an offence to do electrical work unless you're a licensed electrical worker or supervised by one, and as the owner or occupier you must not knowingly engage anyone who isn't allowed to do it. The Act's electrical work includes installing or repairing an installation, altering its structure, and replacing or adding any part of it. Its exceptions, subject to any other written law, include replacing a lamp connected in your own installation, or a fuse in your own installation similar to that of a household.
See our electrical works service.
Aircon
If your condo runs on central air-conditioning, that system is common property and the MCST maintains it. With split units, the outdoor unit and its pipes sit on or near the outside of the building, which can affect how the building looks, so it's a matter for the MCST, and any new power point for them is licensed electrical work.
Plan the pipe and drain routes before the false ceiling goes up. Our article on planning aircon drain pipes during a renovation explains why, and our aircon service covers installation.
Windows, grilles and awnings
Alterations to features fixed on the external building, such as windows and walls aren't allowed without approval from the MCST and any relevant government agencies. Yet you are responsible for the upkeep of features like external openable windows, so ask your MCST which window parts are yours to maintain and replace.
When a window is replaced, BCA says you will need to engage an approved window contractor, and a trained window installer. An approved window contractor is a firm on BCA's register of window contractors (its RW01 category), and a general builder registered with BCA (GB1 or GB2) can also do the work. Where the window doubles as a safety barrier against a drop of 1,000 mm or more, a Professional Engineer designs it and submits plans to BCA, unless BCA's standardised designs are used. Our windows service covers replacement.
Under the strata law, an MCST can't stop you installing safety equipment such as window grilles meant to prevent harm to the people living there, but you have to make sure it doesn't affect how uniform the building looks, so ask for the estate's approved design first.
Awnings and other coverings are different: any addition that may affect the appearance of a building in the estate needs the MCST's permission.
Toilet and bathroom upgrades
If there's a unit below you, your bathroom floor is its ceiling. In an inter-floor leak, it will be presumed that the leak originates from the upper floor unit unless its owner or occupier can prove otherwise, and both sides are expected to investigate together and settle the repair privately.
If you hack the old tiles off a bathroom floor, we recommend a new waterproofing layer, tested before any tile goes back, because hacking can break the old layer without anyone seeing it and the leak risk sits with you. Overlaying new tiles keeps the existing layer, so it only makes sense over a bathroom that isn't leaking now. Our article on waterproofing checks before bathroom tiles go on sets out what to check, and our bathroom renovation service covers condo bathrooms as well.
Leave the shared pipe stacks where they are. Pipes serving two or more units are common property, so plan any new toilet position around the existing stack rather than moving it.
Lofts, balconies and extra space
URA says lofts that are designed as furniture decks can be allowed within a residential unit without planning permission, limited to one per unit and no bigger than 5 square metres.
URA is firm that balconies shall not be enclosed with walls or glass panels, although blinds can go up without planning permission. Open-sided covers over a balcony need the MCST's consent rather than URA's permission.
The order the work goes in
Plan the order before you ask for quotes, because each trade has to finish its part before the next covers it up. This is the sequence we recommend for a condo:
From approval to handover
- 1. Approval and protection. Any approval your estate requires in hand, and the lift and corridor protected the way the guidelines ask.
- 2. Hacking and removal. Walls, old tiles and old carpentry out, with a Professional Engineer's endorsement where your estate asks for one for non-structural walls, and the Commissioner of Building Control's approval for any structural wall.
- 3. Hidden services. New wiring and power points by the licensed electrical worker, plumbing, and aircon pipe and drain routes.
- 4. Wet areas. In the bathrooms, and any wet kitchen floor being redone, the waterproofing layer and a test of it before the tiles go on.
- 5. Ceilings and windows. False ceilings once the pipes and cables above them are in; window replacement by the approved window contractor or registered builder.
- 6. Carpentry. Kitchen cabinets, wardrobes and built-ins, measured on site after the walls and floors are final.
- 7. Painting. After the dusty work, so the walls don't need a second coat.
- 8. Overlay floors and fittings. Floating vinyl after the kitchen units are in, then lights, sanitary fittings and appliances.
- 9. Cleaning and handover. A final clean of the unit and the common areas you used, and whatever the estate asks before it releases your deposit.
Flooring before or after the kitchen and wardrobes
Tiled floors go in before the carpentry. A floating click floor goes in after kitchen units, because the makers in our flooring guide want fixed units installed first, with the floor stopping short of them.
How long a condo renovation takes
Qanvast's January 2025 outlook expected, with no labour or material shortages, around 8 weeks for a new condo and 10 to 12 weeks for a resale condo, which is that site's expectation for its own jobs rather than a promise for yours.
Your own timeline starts earlier, with any approval your estate requires, and it stretches with the estate's permitted hours and any hacking or wall changes.
What drives the cost of a condo renovation
Home & Decor's August 2026 ownership guide says renovation costs generally range from $45,000 to over $100,000 for resale HDB flats or private condominiums, because of the demolition, re-tiling and rewiring they need.
Qanvast, a renovation marketplace, put new condos at $40,400 to $51,500 and resale condos at $80,800 to $105,000 in its January 2025 outlook, projected from 2024 medians of jobs on its platform. These are those publications' ranges, not our prices.
The same Home & Decor guide suggests keeping a 10% to 15% cash contingency for structural variations or hidden piping issues found once hacking starts. Whatever the range, your own bill comes down to how much of the unit is taken out and rebuilt.
What makes one condo cost more than another
- How much comes out. Hacking walls and floor tiles adds demolition and debris removal, plus a Professional Engineer's endorsement where walls come down and your estate asks for one.
- Wet areas. Re-doing a bathroom or kitchen floor brings waterproofing, testing, screeding and tiling.
- Carpentry. Built-in wardrobes and kitchen cabinets, sized to the unit.
- Wiring. New points or a full rewire, done by a licensed electrical worker.
- Windows. Replacement by an approved window contractor or registered builder, and a Professional Engineer if the window is also a safety barrier, unless BCA's standardised designs are used.
- Estate rules. Shorter working hours, lift protection and debris rules add days and handling to the same work.
New condo or resale, what changes
A new unit and a resale unit start from different places, and the biggest difference is who owns the problems you find. The table after the two parts below sums it up.
New condo, defects first
After you collect the keys, URA says you can inspect the unit and report defects to the developer within the 1 year defects liability period. The Sale and Purchase Agreement lists which kinds of defect the developer has to fix.
BCA says any defect reported during the defects liability period remains the developer's responsibility even if it's still unfixed when the period ends, so report everything before you renovate. What we recommend is the order: inspect, report and let the developer fix defects before your contractor covers or changes the same area, and photograph everything first, so nobody can argue later that your renovation caused it.
For the works themselves, BCA says that in a new property you may proceed with minor addition and/or alteration if the works count as insignificant building works, and advises checking with the developer and the project architect or Professional Engineer before major works.
Resale condo, check what's already been done
Before you buy, BCA suggests a competent person, such as an architect, engineer to inspect for unauthorised building works and compare the unit with its approved plans. A lawyer's legal search only shows works already brought to BCA's attention.
This matters because an MCST can serve its rectification notice on whoever owns the unit at the time, so an improvement the last owner made without the approval the strata law required can become yours to undo. Budget for more, too: Qanvast's outlook put resale condos at about twice the cost of new ones, and Home & Decor's contingency advice is for problems found once hacking starts.
What to check first in a new or resale condo, from URA's and BCA's guidance
Scroll across to compare all columns →
| Check | New condo | Resale condo |
|---|---|---|
| Defects | Report them to the developer within the 1 year defects liability period | Yours to repair once the developer's defects liability period is over |
| Earlier works | None yet; minor works can go ahead if they count as insignificant building works | Compare the unit with the approved plans for works that were never approved |
| Cost | About half the resale range in Qanvast's January 2025 outlook | About twice the new condo range in the same outlook, plus a contingency for surprises found during hacking |
How to choose and brief a contractor
Before you compare prices, compare who will actually do the licensed work.
Questions to ask every contractor
- What will you give me for the estate's application? The scope and details of the work its form asks about, with the drawings and any Professional Engineer's endorsement your estate wants.
- Which licensed electrical worker will do the wiring? Ask for the name of the licensed electrical worker who will do or supervise it.
- Who replaces the windows? An approved window contractor or a general builder registered with BCA, with a trained window installer.
- How will the lift and corridor be protected? The answer should match what your estate's guidelines ask for.
- What happens if the plans and the walls don't match? Who stops the work and calls the Professional Engineer, and how a change in scope is priced and approved before it's done.
What to give them
Give every contractor the same pack so the quotes compare: the estate's renovation guidelines, the approved plans, a room-by-room list of what you want changed and which walls you want removed, and a list of any fittings you'll buy yourself. Our article on who's responsible for fittings you supply explains why that list matters.
Start with a site assessment
We start with a free site assessment at your unit, where we look at what you want changed and measure up. You get a fixed-price quote within 3 to 5 working days of that visit, never from a photo. Our specialists do the trade work, we arrange the Professional Engineer or Qualified Person where the work needs one, and we supervise the work and hand it over. Your estate's renovation approval is yours to apply for, and we give you the scope and details of the work its form asks about. Tell us about your unit through our condo renovation service.
Regulatory compliance
Check which requirements apply to your proposed scope. Agree the responsible qualified professionals, submissions and inspections before work begins.
BCA (Building and Construction Authority)
Structural slabs, beams, columns and walls can't be altered without a Professional Engineer's assessment and the Commissioner of Building Control's approval. Windows and external walls need the MCST's approval, and window replacement is done by an approved window contractor or registered builder with a trained window installer. Under the strata law, an MCST can't prohibit safety equipment such as window grilles, but it must not affect the building's uniform appearance.
Primary source: www1.bca.gov.sg/home-and-building-owners/condo-strata/condo-living-be-condo-savvy/what-to-know-as-a-condo-ownerURA (Urban Redevelopment Authority)
Internal works in a condo unit don't need planning permission when floor area doesn't increase and the unit stays one self-sufficient home. Balconies can't be enclosed with walls or glass panels, one loft designed as a furniture deck, up to 5 square metres, can be allowed without planning permission, and works that add floor area need the MCST's 90% resolution with the planning application.
Primary source: www.ura.gov.sg/guidelines/property-and-business-owners/property/renovating-private-residential-property/strata-titled-residentialEMA (Energy Market Authority)
The Electricity Act 2001 makes it an offence to do electrical work unless you're a licensed electrical worker or supervised by one, with exceptions such as replacing a lamp in your own installation, subject to any other written law.
Primary source: sso.agc.gov.sg/Act/EA2001?ViewType=PdfNEA (National Environment Agency)
NEA regulates noise from additions and alterations works in landed homes. For renovation noise from condo units, it directs residents to the estate's MCST.
Primary source: www.nea.gov.sg/our-services/pollution-control/noise-pollution/construction-noise-control/information-on-noise-from-renovation-work-in-residential-areasGlossary
- MCST
- Management Corporation Strata Title, the body of all the unit owners in a condo. It manages the common property and makes the by-laws.
- Subsidiary proprietor
- The legal name for a unit owner in a strata development. It's the term you'll see on MCST forms and in BCA's guides.
- By-laws
- The estate's own rules, passed at general meetings. They sit on top of the prescribed by-laws every estate has to follow.
- Common property
- The parts of the estate that aren't inside any unit, plus structural elements, shared pipes and cables and the external walls, even where they run through your unit.
- Strata title plan
- The registered plan that shows where your unit ends and common property begins.
- Professional Engineer (PE)
- An engineer registered with the Professional Engineers Board. A PE assesses structural changes, and endorses renovation plans for non-structural demolition where the MCST asks.
- Qualified Person (QP)
- A registered architect or Professional Engineer with a valid practising certificate who submits plans to BCA and supervises approved building works.
- Licensed electrical worker (LEW)
- An electrician, electrical technician or electrical engineer licensed by the Energy Market Authority to carry out or supervise electrical work.
- Approved window contractor
- A firm on BCA's register of window contractors that installs and replaces windows with a BCA-certified trained window installer. A general builder registered with BCA can also do the work.
- Defects liability period (DLP)
- The period after you collect the keys to a new unit when the developer has to fix reported defects, which URA describes as 1 year.
Frequently asked questions
Do I need MCST approval to renovate my condo?
Check before you start. BCA says building works in condos might require MCST's approval, and your estate's by-laws and renovation guidelines say which works need it. Structural changes also need a Professional Engineer and the Commissioner of Building Control, and windows need the MCST's approval. Our article on MCST approval for condo renovation walks through the application.
Can I enclose my condo balcony with glass?
URA is firm that balconies shall not be enclosed with walls or glass panels, although blinds can go up without planning permission. Open-sided covers over a balcony, private enclosed space or roof terrace don't need URA's permission, but they do need your MCST's consent and have to meet BCA's and the Singapore Civil Defence Force's requirements where they apply.
Can I build a loft in my condo unit?
URA says lofts that are designed as furniture decks can be allowed within a residential unit without planning permission, limited to one per unit and no bigger than 5 square metres. Work that adds floor area, such as roofing over a private enclosed space, needs a 90% resolution of your MCST, and URA's and BCA's approval may be needed depending on the work.
Can I install window grilles in my condo?
Under the strata law, an MCST can't stop you installing safety equipment such as window grilles meant to prevent harm to the people living there, but you have to make sure it doesn't affect how uniform the building looks, so ask for the estate's approved design first. A grille that matches the estate's existing ones is the simplest to get through.
Where can I get the floor plan for my condo unit?
For the approved plans of your unit, BCA sells copies through its Plan Purchase Application Form, and the strata title plan, which shows where your unit ends and common property begins, can be obtained from the Singapore Land Authority at a cost. Ask your management office first, since BCA has advised MCSTs to keep the approved structural plans for you to plan a renovation with.
What happens if I renovate my condo without approval?
If improvements were made to a unit without the approval the strata law requires, the MCST may serve a notice requiring the owner at the time to put them right at their own cost, and if they don't, it may do the work and recover the cost. Separately, BCA says that if you're found with unauthorised building additions and/or alterations, you'll have committed an offence under the Building Control Act.
What can I do if my MCST won't approve my renovation plans?
Start by asking what would make them acceptable. Your MCST approves renovation in the estate, and BCA's advisory notes it can impose conditions before approving, so that the building's key structural elements aren't affected. A Professional Engineer's endorsement is one condition your estate may ask for. You can raise a by-law you think is unfair at the next general meeting. If you can't settle it with the management, BCA points you to mediation at the Community Mediation Centre or Singapore Mediation Centre, or to the Strata Titles Boards.
Which professionals does a condo renovation need?
The people the rules name depend on the work: a Professional Engineer's assessment and the Commissioner of Building Control's approval for structural walls, a Professional Engineer's endorsement for other walls where your MCST asks for one, a licensed electrical worker for wiring, and an approved window contractor or registered builder with a trained window installer for windows. BCA also advises you, as a private property owner, to engage a Qualified Person to advise on the clearances required, which means a registered architect or Professional Engineer. None of the rules above name an interior designer, who helps with the layout and look.
If you read nothing else
Talk through the options for your home
Tell us what you want to change, how your household uses the space and when you hope to start. Share photos or plans on WhatsApp if you have them.
Browse all condo renovation articles →
Go deeper: condo renovation articles
In-depth pieces that expand on the sections above: real costs, brand and system comparisons, the installation process, and the edge cases most homeowners hit.
Still deciding? Compare options & estimate cost
Side-by-side comparisons and an instant cost estimate for your Singapore home.
Related guides
Buying Guide
How to choose the best vinyl flooring for your home
Know which vinyl to lay in each room, where tile or real parquet does the job better, and which old floors can stay underneath.
Buying Guide
Choosing bathroom fixtures and fittings for a landed home
In Singapore a PUB Licensed Plumber must install or move a toilet, while a handyman may fit a shower enclosure or swap a tap.
Buying Guide
Is ducted aircon right for your landed home?
Ducted aircon hides the unit in the ceiling but needs depth, a return air path and access doors. Here is when a cassette or wall-mounted unit suits better.