Under the Building Control Regulations, replacing floor and wall tiles or removing a wall that carries only its own weight needs no plans sent to the Building and Construction Authority (BCA). A wall that holds up more is structural, needing an engineer's assessment, an approved plan and a permit first. Your estate or landlord may need to approve either job.
So the first question isn't the price. It's what's coming out and what it's holding up. This guide takes the questions in the order you'll meet them: which walls can go, what a condo estate or a landlord decides, floors and bathrooms, what's behind the wall, noise and debris, and what drives the cost of a hacking quote.
If you'd rather have one firm look at the job, our hacking and demolition service starts with a free site assessment. Our specialist does the hacking. Where a wall may be structural, we arrange a Professional Engineer to assess it.
What hacking covers, and what it doesn't
Hacking is breaking out what's built into your home or unit, so something new can go in or the space can go back to bare.
The jobs it takes in
- Walls and partitions. Brick, block or board walls, or a doorway cut into one.
- Floor tiles. The tiles alone, or the tiles and the cement bed they sit on.
- Wall tiles. In a kitchen, a bathroom or anywhere else they were laid.
- Kitchens and bathrooms. Cabinets, worktops, fittings and tiles, stripped back to bare walls and floor.
- Built-ins and false ceilings. Wardrobes, shelving, raised platforms and suspended ceilings.
- A commercial strip-out. Partitions, ceilings and flooring taken out of a shop, office or factory unit.
What it isn't
Knocking down a whole house or building is demolition on another scale, and it's outside this guide. So are Housing and Development Board (HDB) flats, because HDB issues its own permits for renovation work in HDB units.
Which walls you can hack, and when an engineer comes in
Whether a wall can come down depends on what it carries, and that answer comes from the approved plans and an engineer.
What can come out without plans
The Building Control Regulations list the insignificant building works that don't require plan submission to BCA. For hacking, that list includes the demolition, restoration or reinstatement of any non-load bearing wall, the replacement of existing floor and wall finishes, and the demolition of a false ceiling suspended from the main structural ceiling, with any supporting system used only to hold it up. The table at the end of this section sets them out.
The same regulations define a non-load bearing wall as one that supports no load other than its own weight.
No plans to BCA doesn't mean no approvals. BCA says that even then you must observe safety and good practices and obtain the required approvals from other relevant authorities. In a condo or a rented unit, your estate or landlord may need to approve the work too, as the next two parts explain.
Who decides whether a wall is structural
Ask an engineer, not the contractor. In BCA's sample certificate for renovation plans, the Professional Engineer has personally checked the approved structural plan and inspected the structural condition of the unit before certifying that no structural element will be altered or demolished.
So start with the plans. BCA has advised condo estates to keep a full set of approved structural plans for anyone in the estate planning a renovation, so ask your management office first. You can also buy copies of your property's approved plans from BCA through its Plan Purchase Application Form.
Watch out
Knocking on a wall doesn't tell you what it carries. The regulations define a non-load bearing wall by the load it supports, not by how it sounds.
When the wall is structural
In a condo, BCA says structural elements such as slabs, beams, columns and walls can't be altered without proper assessment by a Professional Engineer, and approval from the Commissioner of Building Control is also required.
In any building, structural works need an approved structural plan and a permit before they start. Only a Professional Engineer in the civil or structural discipline can apply for the plan approval, while the permit is applied for jointly by you, the Qualified Person (QP, a registered architect or Professional Engineer) and the builder who will carry out the works. Where a wall you want removed may be structural, we arrange a Professional Engineer to assess it. The assessment and the structural plan application are the engineer's.
On timing, BCA's page, last updated 20 August 2026, says a structural plan application without an accredited checker's certification is processed within 7 working days of complete documents, and a permit to carry out structural works within 7 working days. That plan approval time applies only to an application that meets the requirements the first time; one that needs more extensive evaluation may take longer.
Skipping this has consequences. BCA says building owners found with unauthorised building additions and/or alterations will have committed an offence under the Building Control Act. In its 2014 advisory to condo estates, BCA noted cases of unauthorised demolition of structural elements during renovation, some of which led to Dangerous Building Orders being served on the management corporation. Our article on whether you need approval to hack a wall goes through each case.
Landed houses and party walls
In a landed house, a structural change can count as additions and alterations (A&A) work. Take care with the party wall, the wall your house shares with your neighbour's. The Urban Redevelopment Authority (URA) and BCA's guide for landed estates, which describes itself as advisory, says that generally there should be no hacking of the existing party wall to create a recess to embed new walls, columns or beams, and that your contractor shouldn't use it as formwork (the temporary mould for new concrete) or support.
Which hacking jobs are on the Building Control Regulations' list of insignificant building works, which need no plan submission to BCA (First Schedule, version in force from 17 April 2026)
Scroll across to compare all columns →
| Job | What the list says | What still applies |
|---|---|---|
| Taking down a wall | The demolition, restoration or reinstatement of any non-load bearing wall, meaning one that supports no load other than its own weight | Ask an engineer, not the contractor, whether the wall is non-load bearing; any approval your estate, landlord or another authority requires |
| Replacing floor or wall tiles | Replacement of existing floor and wall finishes | Any approval your estate, landlord or another authority requires |
| Taking down a false ceiling | Demolition of a false ceiling structure suspended from the main structural ceiling, with any supporting system used solely to support it | Any approval your estate, landlord or another authority requires; in a shop or office, whether the work affects escape routes or fire compartments |
| Taking down or cutting into a structural wall, beam or column | Not on the list | A Professional Engineer's assessment, an approved structural plan and a permit before work starts |
What your condo estate decides, and what you share with the unit below
Your management corporation (MCST) runs the estate's renovation rules, and some of what you'd hack into is shared with the other owners.
What your estate decides
BCA says building works in condominiums might require the MCST's approval, and its condo page says there are restrictions on hacking or additional work allowed in your unit and that you should check with the developer or the MCST and your Sale and Purchase Agreement before any work. Get the estate's by-laws and renovation guidelines before you book anyone. They can set the working hours, any deposit, how the lift and corridors are protected and how debris leaves.
For walls, BCA's 2014 advisory suggested that before approving the demolition of non-structural elements other than floor tiles, estates ask for renovation plans endorsed by a civil or structural Professional Engineer certifying that no structural works are involved, and that any demolition other than floor tiles be done by contractors with trained workers certified by BCA Academy. It's advice to estates, so yours may or may not ask for either. The estate's approval is yours to apply for. When we do the work, we give you the scope and the details the estate's form asks about.
What's shared with the unit below
Under the strata law, now the Building (Strata Management) Act 2004, any structural element of the building is common property, and so are pipes, wires, cables and ducts used by two or more units, even where they run through yours. BCA's summary of the 2018 changes says slabs, excluding the underlayment, became common property. So the tiles and the underlayment on top of your floor slab are generally on your side of the line, while the slab itself is shared, and it's one of the structural elements BCA says need an engineer's assessment.
That slab is also your downstairs neighbour's ceiling. If water gets through, BCA's strata guide says it will be presumed that the leak originates from the upper floor unit unless its owner or occupier can prove otherwise. Hacking a bathroom or kitchen floor puts that risk with you, which is why the bathroom part below matters.
In a rented shop, office or factory unit, start with your lease
In a rented unit, what you can hack out, when the work can run and what goes back at the end are set by your lease and your landlord, so read both before you plan anything.
Ask your landlord or building management for their fitting-out rules and approval process, and ask in writing about anything the lease leaves unclear. In premises leased from JTC, the government agency that leases industrial land and space, all fitting-out or renovation works need JTC's and the relevant authorities' approval before they start, and JTC asks you to check with its facility management team whether you have to use the building's appointed contractor.
At the end of a JTC lease, you're required to reinstate your premises before returning them on the lease expiry date. JTC arranges a joint site inspection approximately 6 months before the lease expires, then tells you the reinstatement requirements, taking your lease's obligations into account. With any other landlord, the reinstatement clause in your lease sets what has to come out.
Taking out partitions or a ceiling may also count as fire safety works if it changes the layout of spaces in a way that affects escape routes, or affects fire compartments, which need the Singapore Civil Defence Force's (SCDF) plan approval first unless an exemption or its minor works lodgement covers them. Our article on approvals for commercial renovation explains which applies. If the handover needs more than hacking, our commercial renovation service covers the rest of the fit-out or reinstatement.
Hack or overlay your floor tiles, and what hacking a bathroom means
Overlay or hack
Overlaying lays the new floor over your old tiles. Hacking takes the old tiles out first, and sometimes the cement bed under them.
Overlay skips the hacking, with its noise, dust and debris, which counts where an estate limits noisy hours. But it raises the floor everywhere it goes, so the main door, every internal door, the step into the bathroom and the first stair have to work at the new height. Old tiles that have lifted or cracked may need to come up anyway, and a wet area you're redoing is a reason to hack rather than cover.
Our flooring guide explains which floors suit an overlay, our article on whether overlay or hacking costs less works through the trade-offs, and our flooring service lays the new floor either way.
Hacking a bathroom
If you're hacking a bathroom floor, plan to waterproof it again. We recommend a new waterproofing layer, tested before any tile goes back, because hacking can damage the old layer in ways nobody can see, and in a condo the leak presumption above puts the risk on you.
Plan any moved toilet, basin or floor trap at the same time, since the pipes are easiest to reroute while the floor is open. Our article on waterproofing checks before bathroom tiles go on sets out what to check, and our bathroom renovation service covers the rebuild.
What's behind the wall, and what your quote should say about it
Hacking opens up what has been covered since the building went up: pipes, cables, the structure itself and, in an older building, possibly asbestos. Agree before work starts what happens if each one turns up.
Pipes and cables
In a condo, the shared ones are common property, as the condo part above explains, and BCA's strata guide says you can't alter common property without the management corporation's permission. Plan around them rather than moving them.
A cable that has to move is electrical work, and our electrical works service covers rewiring once the hacking is done.
Ask for a quote that says what happens when a pipe or cable turns up where nobody expected it: work stops on that spot, you're shown it, and any change is priced and agreed before it's done.
Steel in the wall or floor
BCA's advisory to condo estates says that whenever the structural reinforcement bars are exposed, the works shall be stopped and a Professional Engineer called in to assess and recommend remedial measures, with BCA notified. Whatever kind of home you have, we recommend the same order: stop, call the engineer, and decide nothing until the assessment is in.
Asbestos in older buildings
The age of your building matters here. The Ministry of Manpower (MOM) says Singapore banned asbestos in building materials in the late 1980s, and that a building built after 1 January 1991 is unlikely to contain asbestos-containing materials. For buildings built before then, MOM says asbestos surveys are required for any building work, which it says covers alteration, addition or repair. MOM says you'll also need a survey for work on certain materials listed in the asbestos regulations, such as fire protection boards, panels, walls and doors, cable penetration insulation and the thermal insulation of pipes, unless there's documented proof the material contains no asbestos.
If a survey finds asbestos that is damaged or will be affected by the renovation, MOM says you should consider removing it. Removal has to be done by one of MOM's Approved Asbestos-Removal Contractors, who must notify MOM at least 1 week before the work starts. If your building went up before 1991, or the work touches one of those listed materials, ask about the survey before you fix a start date.
Noise, debris, and where hacking fits in a renovation
Noise and your neighbours
Who handles noise depends on where you live. In a condo, the National Environment Agency (NEA) says residents affected by renovation noise may give feedback directly to their MCST, so look to your estate's guidelines for when noisy work like hacking can run. In a landed house, NEA regulates noise from A&A works, points you to its construction noise rules for the allowable working hours and noise limits, and takes feedback through its online form. In a shop or office, ask your landlord.
The simplest way to avoid complaints is to tell your neighbours first. URA and BCA's landed guide advises informing them of your plans and the estimated duration of construction. In a condo, ask your management office how it lets neighbours know.
Dust and debris
NEA's code for waste collectors counts construction and renovation debris as general waste, which no person or company shall collect or transport as a business without NEA's General Waste Collector's Licence. Check that your quote says who carries the debris away.
For dust, ask how the work area will be sealed off from the rest of your home and from shared corridors, and how the rooms that stay will be covered.
Where hacking sits in the order of works
Hacking goes first, because everything after it covers up what it opens. This is the order we recommend:
- 1. Approvals and assessments. Whatever your estate, landlord or BCA requires, the engineer's assessment of any wall that may be structural, and an asbestos survey where MOM requires one.
- 2. Protection. Floors, lifts and corridors covered the way your estate or building asks.
- 3. Hacking and debris out. What the quote lists, and nothing more without your say.
- 4. Pipes, cables and aircon routes. Laid while the walls and floors are open.
- 5. Screeding and waterproofing. Floors levelled, and wet areas waterproofed and tested before any tiling.
- 6. Tiling, ceilings, carpentry and painting. The finishing trades, once the surfaces are ready.
What drives the cost of hacking, and how to compare two quotes
The bill follows what comes out, how deep it goes and how the debris gets out of the building. However a quote is laid out, by area, by wall or as one sum, compare the scope behind the figure.
Why two quotes for the same home differ
When two quotes for the same home differ, check the scope before the price. One may have priced the cement bed under the tiles and the other not, or one may include the engineer, the protection and the making good while the other leaves them for later. The table below sets out what to check on each line.
At the end of a lease, price the reinstatement from what your lease and landlord require to go back, not just from what comes out.
How to choose and brief the job
Give every contractor the same brief so the quotes compare: a room-by-room list of what comes out and to what depth, the approved plans if you have them, your estate's renovation guidelines or your lease's fitting-out and reinstatement clauses, and the year your building was completed.
Then choose on the answers, not the total. The quote that prices every line in the table below, in writing, is the one you can hold to.
Start with a site assessment
We start with a free site assessment, where we look at what you want taken out and measure up, and send a fixed-price quote within 3 to 5 working days of it, never from a photo. Our specialist does the hacking, and we supervise the job through to handover. Where a wall may be structural, we arrange the engineer. Tell us what's coming out through our hacking and demolition service.
Lines to check on a hacking quote, and why each one moves the price
Scroll across to compare all columns →
| On the quote | Why it moves the price | What it should say |
|---|---|---|
| What comes out | A board partition is less work than a brick wall, and tiles alone are less than tiles with the bed under them | Room by room, and to what depth |
| Kitchen and bathroom strip-outs | Cabinets, fittings and wall tiles add to the floor | Which fittings come out, and whether any are kept |
| Structural walls | An engineer's assessment and any approval come first | Who arranges the engineer's assessment |
| Protection | Covering floors, lifts and corridors takes time and material | How each is covered, to your estate's or building's rules |
| Debris | Carrying it down and away, by a licensed collector | Who takes it away, and when |
| Making good | Patching edges and levelling floors after the hacking | What's patched or levelled, and to what standard for the next trade |
| Working hours | Shorter hours for noisy work stretch the same job over more days | The hours the price assumes |
| Surprises | Pipes, cables, steel or asbestos change the job | What happens if any of them turns up, and how a change is agreed |
Regulatory compliance
Check which requirements apply to your proposed scope. Agree the responsible qualified professionals, submissions and inspections before work begins.
BCA (Building and Construction Authority)
Structural works need an approved structural plan and a permit before they start; only a civil or structural Professional Engineer applies for the plan approval, and the permit is applied for jointly by you, the Qualified Person and the builder. In a condo, structural elements such as slabs, beams, columns and walls can't be altered without a Professional Engineer's assessment and the Commissioner of Building Control's approval. Works on the Building Control Regulations' list of insignificant building works, such as demolishing a non-load bearing wall, need no plan submission, but other approvals may still apply.
Primary source: www1.bca.gov.sg/safety-and-standards/applications-and-licenses/structural-plan-submissionNEA (National Environment Agency)
NEA regulates noise from A&A works in landed homes; residents affected by renovation noise from a condo unit may give feedback to the estate's MCST. Construction and renovation debris is general waste, which no person or company shall collect or transport as a business without NEA's General Waste Collector's Licence.
Primary source: www.nea.gov.sg/our-services/pollution-control/noise-pollution/construction-noise-control/information-on-noise-from-renovation-work-in-residential-areasMOM (Ministry of Manpower)
Asbestos surveys are required for any building work in buildings built before 1 January 1991, and for work on certain listed materials, such as fire protection boards and pipe insulation, unless there's documented proof they contain no asbestos. If you remove asbestos-containing material, you must engage one of MOM's Approved Asbestos-Removal Contractors, who must notify MOM at least 1 week before the work starts.
Primary source: www.mom.gov.sg/faq/notify-for-asbestos-work/when-do-i-need-to-conduct-an-asbestos-surveySCDF (Singapore Civil Defence Force)
Fire safety works, which include layout changes affecting escape routes and works affecting fire compartments, need SCDF's plan approval before they begin, unless an exemption or a minor works lodgement covers them.
Primary source: www.scdf.gov.sg/fire-safety-services-listing/plans-submission-process/plan-approvalJTC (JTC Corporation)
In JTC premises, fitting-out and renovation works need JTC's and the relevant authorities' approval before they start, and you're required to reinstate your premises before returning them on the lease expiry date.
Primary source: www.jtc.gov.sg/get-help/development-and-renovation-works/fitting-out-and-renovation-worksGlossary
- Insignificant building works
- The works listed in the First Schedule of the Building Control Regulations, such as demolishing a non-load bearing wall or replacing floor and wall finishes, which don't need plans submitted to BCA.
- Non-load bearing wall
- In the regulations' words, a wall that supports no load other than its own weight.
- Professional Engineer (PE)
- An engineer registered with the Professional Engineers Board. A civil or structural PE assesses structural walls and applies for structural plan approval.
- Qualified Person (QP)
- A registered architect or Professional Engineer with a valid practising certificate, who advises on the clearances building works need.
- Commissioner of Building Control
- The BCA official who approves structural plans and grants the permit for structural works to start.
- Common property
- In a condo, usually the parts of the estate outside any unit, plus some parts inside yours that the strata law names, such as structural elements.
- Making good
- Repairing the edges and surfaces a hacking job leaves behind, such as patching walls or levelling a floor, so the next trade can work on them.
- Reinstatement
- Returning a rented unit to the condition your lease requires before you hand it back.
Frequently asked questions
Can I knock a doorway into a wall without sending plans to BCA?
If the wall is non-load bearing, yes as far as BCA goes. The Building Control Regulations list the creation of any opening in a non-load bearing wall, or the sealing up of any wall opening, among the works that need no plan submission. Ask an engineer, not the contractor, whether the wall is non-load bearing. An opening in a structural wall is structural work, with an engineer, an approved plan and a permit first. In a condo or rented unit, your estate or landlord may need to approve either.
After a wall comes down, can I put up a new partition without plans?
The same list covers the erection or alteration of any partition up to 10 metres high, with its supporting system, on conditions. In a bungalow, semi-detached, terrace or linked house, any non-laminated glass in it must sit no more than 2.4 metres above the floor. In any other building, the partition has to be built of lightweight material, which the regulations define to include boards such as plasterboard or gypsum board, hollow concrete or glass blocks and autoclaved aerated concrete blocks. Your estate or landlord may still need to approve it.
Does taking out a loft need plans sent to BCA?
Not if it's a loft of timber or steel construction. The regulations' list includes the removal of any loft of timber or steel construction, so that needs no plan submission to BCA, though in a condo your estate may still ask for an engineer's endorsement, as the condo part above explains. For any other loft, mezzanine or platform, BCA says a permit is required for all building works except those on the list, so ask an engineer, not the contractor, before anyone quotes for taking it out. Our article on commercial renovation approvals covers mezzanines and storage platforms in a shop or factory unit.
Can pipes be run through the floor slab when a toilet or basin moves?
Without plans to BCA, only within tight limits. The regulations' list includes forming an opening in a slab for building services that alters no other structural element, but not in a cantilever slab, a flat slab or any prestressed element. Unless it's a ground slab, a round opening can be no more than 150 mm across, a square or rectangular one no more than 150 mm a side, and if the slab already has an opening, the new one's centre must be at least 450 mm from the edge of any other opening. An engineer can tell you what kind of slab yours is, and anything beyond those limits needs plans. In a condo, the slab is common property, and BCA's strata guide says you can't alter common property without the management corporation's permission, so ask your MCST before anyone cuts into the slab.
I've just collected the keys to a new condo. Can I start hacking?
Report defects first. BCA says any defect reported during the Defects Liability Period remains under the developer's responsibility even if it's still unfixed when the period ends, so inspect and report before your contractor covers or removes anything. For the works, BCA says that in a new property you may proceed with minor addition and/or alteration if they're insignificant building works, and advises checking with the developer and the project architect or Professional Engineer before major works.
If you read nothing else
Talk through the options for your home or unit
Tell us what you want to change, how you use the space and when you hope to start. Share photos or plans on WhatsApp if you have them.
Browse all hacking and demolition articles →
Go deeper: hacking and demolition articles
In-depth pieces that expand on the sections above: real costs, brand and system comparisons, the installation process, and the edge cases most homeowners hit.
Still deciding? Compare options & estimate cost
Side-by-side comparisons and an instant cost estimate for your Singapore home.
Related guides
Buying Guide
How to plan a condo renovation in Singapore
What's yours to change in a condo unit, what to get from your estate, who approves each kind of work and how to brief a contractor.
Buying Guide
How to choose the best vinyl flooring for your home
Know which vinyl to lay in each room, where tile or real parquet does the job better, and which old floors can stay underneath.
Buying Guide
How to plan a commercial renovation in Singapore
What to settle with your landlord before you sign, who approves which works, how each trade works in an office, shop or factory unit, and how to compare fit-out quotes.