Part of our complete guide
Home Lifts in Singapore: A Landed Home Buying Guide →Start to Finish: 6 to 10 Weeks
Request a project programme covering survey, coordinated design, submissions where required, equipment procurement, site preparation, installation, testing and the PTO application. The equipment and building interfaces determine the schedule; a regulated lift must have a valid PTO before use.
Below is the realistic week-by-week breakdown we walk every client through during the first site visit. Treat it as a guide. Every home throws up something unexpected, but the broad shape holds.
Sources: Building and Construction Authority: Fixed Installations owner requirements
Step 1: Site Visit and Feasibility (Week 0)
We come to your home, take measurements of the proposed lift location, check the ceiling height, look at the floor slab, and trace where the electrical sub-DB sits. The goal is to confirm a lift is structurally possible and which type makes sense. This visit is free and takes about 60 minutes.
If your home has an existing stairwell void or a lift provision left by the original architect, this step often confirms within minutes that the project is straightforward. If the lift needs to go through an existing slab, we flag the structural consultant we will need to involve.
Step 2: Quote, Contract, and BCA Submission (Weeks 1 to 3)
Within three to five working days of the site visit you receive a written quote with full scope, timeline, and a payment schedule. Once you sign, we submit to BCA for installation approval. This step requires the appointed Specialist Builder to lodge structural drawings, lift specifications, and a Qualified Person sign-off.
BCA processing typically takes two to three weeks. While we wait, the lift is ordered from the manufacturer, which is important because European-built units have lead times of 6 to 14 weeks. The two timelines usually overlap so the lift arrives roughly when BCA approval comes through.
Step 3: Structural and Shaft Works (Weeks 3 to 6)
Once BCA approval is in, we mobilise on site. For homes without an existing shaft this is the noisiest phase: slab cutting, structural steel installation, shaft construction, and electrical sub-DB upgrade. Plan for noise during working hours and dust on the work-area floors despite our sealing.
Homes with an existing shaft or void skip most of this. Vacuum lifts also skip most of this because the tube is self-supporting. In the best case, structural works compress to one week. In the toughest retrofits, typically older terrace homes with no provision, it can stretch to four.
Step 4: Lift Installation (Weeks 6 to 8)
The lift unit arrives on site in crates. The installation crew assembles the rails, fits the cabin, connects the drive system, runs the control wiring, and tests the mechanical operation. This phase is more skilled and less disruptive: typically two technicians on site for 5 to 10 working days.
You can usually continue living in the home during this phase. The work concentrates around the shaft and machine cabinet, with limited disruption to bedrooms or kitchens. We brief the crew to clean up daily so weekends remain liveable.
Step 5: Testing, Certification and Permit to Operate
After installation, have the responsible professionals and registered FI contractor coordinate the required testing, certification and PTO application for the new lift. Confirm the applicable process and completion records with them. The ongoing annual inspection/testing duty is separate from routine maintenance.
A regulated lift must have a valid Permit to Operate before it is used. Physical installation alone does not establish that it is ready for lawful operation; retain the permit and completion records with the equipment documentation.
Sources: Building and Construction Authority: Fixed Installations owner requirements
Step 6: Handover and Owner Training (Week 9 to 10)
At handover, ask the provider to demonstrate normal operation, the installed emergency communication features and the model-specific power-failure behaviour. Obtain the PTO, manufacturer manuals, service agreement and support contacts. Do not assume every system provides a household-operated manual-lowering procedure.
If anything is not right at the walkthrough, whether a finish detail, a missing fitting, or a noise that should not be there, we fix it before signing off. WhatsApp DirectHome at +65 8886 6590 if you want to start the process. The first site visit is free and gives you a realistic timeline for your home.
Sources: Building and Construction Authority: Fixed Installations owner requirements
Sources and scope
Our editorial team checked the references below. Manufacturer guidance applies to the products and arrangements it describes; confirm the documents for your proposed installation.
- Fixed Installations owner requirements
Building and Construction Authority · Checked
Current maintenance schedule for a lift serving a single residential unit, annual inspection and testing, registered FI contractors and valid PTO requirement. This source does not substantiate market prices.
Related Services
Home Lifts across Singapore
We deliver home lifts for landed homes in:
Need Help With Your Project?
Get a free site assessment and no-obligation quote.
About the author
Written by the DirectHome team, Singapore home-upgrade contractors coordinating licensed lift, pool, roofing and gate specialists. We coordinate BCA-permitted works through licensed specialist partners across landed property in Singapore.


