View In PDFWhatever your lease's reinstatement clause lists has to come out, so ask your landlord to set out the detail in writing. That can include partitions, false ceilings, flooring and wiring you added. Taking out sprinklers, exit signs or wiring can also bring in a Qualified Person and the Singapore Civil Defence Force (SCDF), or a licensed electrical worker, so plan those first.

Here's how to get that list, who has to handle each part, and how to time it against your handover date. Our commercial renovation service quotes reinstatement from your lease, and our hacking and demolition service covers taking out partitions, ceilings and floors that aren't structural.
What reinstatement means for your unit
Reinstatement puts the unit back the way your lease says it goes back. Words like "original condition" and "bare shell" mean what your lease and the records from when you took the unit describe, so read the clause, and find the floor plan, drawings or photos from your move-in.
If you lease from JTC Corporation, JTC says you are required to reinstate your premises before returning them on the lease expiry date. After a joint site inspection, it tells you the reinstatement requirements, taking into account the reinstatement obligations in your lease.
For an HDB shop or office, HDB says you need to restore the premises to its original condition, including removal of all furniture, fixtures and fittings, in line with your tenancy agreement. If you don't, HDB carries out the reinstatement works and recovers the costs from you.
In a mall or a private office building, ask the landlord or its managing agent for the list, and check it against your lease. The building's renovation rules can also set the working hours and how the lift and corridors are protected, so get those too.
Get the reinstatement list in writing first
Quotes, approvals and your timetable all hang on one document, the landlord's list of what comes out and what can stay. Ask for it in writing, and ask about each of these.
Ask your landlord in writing
0 of 5 reviewed
Use this to track your review. Checks stay on this page while it is open.
Before you leave a floor you think is in good condition, get the landlord's agreement in writing. If the list says it comes out, have it priced to come out.
Who has to handle each part of the fit-out
Taking a fit-out apart isn't one trade. Some items come out with nothing more than the landlord's list, and others bring in someone the law names.
| What comes out | What the rules add | Who handles it |
|---|---|---|
| Partitions that carry only their own weight | Demolishing or reinstating a non-load bearing wall is on the Building Control Regulations' list of insignificant building works, which the Building and Construction Authority (BCA) exempts from a permit | The demolition contractor, once the wall is confirmed to carry nothing but itself |
| False ceilings holding sprinklers, smoke detectors or exit signs | Removing or relocating fire protection systems counts as fire safety works | A Qualified Person, who submits plans or lodges the works with SCDF first, unless the works are exempt |
| Partitions or doors that change escape routes or fire compartments (the sections of a building built to hold a fire back) | Also fire safety works, including replacing fire doors | A Qualified Person, as above |
| Wiring, sockets, lighting or a sub board (a smaller switchboard) you added | Any work on an electrical installation is electrical work | A licensed electrical worker, or someone working under one |
| Anything that may be structural, such as a mezzanine floor | Building works outside BCA's insignificant list need a permit | An engineer, who assesses it first |
| Debris, old furniture and fittings | Construction and renovation debris is general waste | A collector holding a General Waste Collector's Licence from the National Environment Agency (NEA) |
For walls, the Building Control Regulations list the demolition, restoration or reinstatement of any non-load bearing wall among insignificant building works, and a non-load bearing wall is one that supports no load other than its own weight. BCA says a permit is required for all building works, except for those classified as insignificant building works.
If there's any doubt about what a wall or a mezzanine carries, have it checked before anyone hacks it. Where a reinstatement needs that, we arrange the engineer.
Taking out a fit-out can still need SCDF

It's easy to assume removal needs no approval, because nothing new is going in. SCDF's plan approval page says that under the Fire Safety Act 1993, any person who intends to carry out fire safety works in a building must first obtain approval of plans from SCDF.
Those works include any installation, addition, alteration, removal or relocation of fire protection systems, such as hose reels, fire alarm panels, sprinklers, emergency exit signs and fire doors. They also include changes in the layout of spaces that affect escape routes, or works affecting fire compartments.
The plans are prepared and submitted by a Qualified Person, a registered architect or professional engineer, on behalf of the building owner or occupier. Works covered by the Fire Safety (Exemption) Order need no plan submission, and some minor works may proceed after a minor additions and alterations (MAA) lodgement; in all other cases, SCDF's plan approval is needed before work can begin.
For MAA works, SCDF says the applicant or tenant needs the consent of the building owner or management corporation before carrying out the works. When a removal touches the sprinklers, alarms or exits, we arrange the Qualified Person, so any submission SCDF needs is made before the work starts.
Wiring and debris have their own rules
The Electricity Act counts any work performed or carried out on any electrical installation as electrical work. It says an individual must not carry out electrical work unless they are a licensed electrical worker or act under the supervision of one, and that an owner or occupier of any premises who wishes to have any electrical work carried out there must not knowingly engage anyone who isn't allowed to do it.
So disconnecting and taking out the wiring, sockets and boards you added is electrical work, and by law it must be done by a licensed electrical worker or under one's supervision. If you'd like that arranged with the rest of the job, that's what our electrical works service is for.
NEA's code for waste collectors counts unwanted furniture, electrical appliances and construction and renovation debris as general waste, and says no person or company shall collect or transport general waste as a business without a valid General Waste Collector's Licence issued by NEA. Ask each quote who carts the debris away, and under whose licence.
Work back from your handover date

Under a JTC lease, the dates are set out for you. JTC says you get an email reminder 1 year before your lease expires, and it arranges a joint site inspection approximately 6 months before the lease expires.
Reinstatement works must be completed before the lease expiry date, and if they aren't, you are liable to pay double rent from that date. If your business used pollutive materials, you may also need an Environmental Site Assessment before you hand the unit back.
Those are JTC's terms. With any other landlord, your lease sets the notice, the inspection and what a late handover costs, so read those clauses now rather than in the last month.
We recommend working in this order, so nothing holds up the handover:
- Get the landlord's written list, and agree anything that can stay.
- Get any SCDF submission and the building's own approvals in place.
- Have a licensed electrical worker disconnect and take out the added wiring.
- Take out the fit-out, cart the debris away and make good (patch and repair) what stays.
- Walk the unit at the joint inspection and fix anything it finds.
- Hand back the keys before the lease ends.
Leave enough time before the lease ends to walk the unit twice, in case the first inspection finds something to fix.
What to ask for in a reinstatement quote
You can only compare quotes that price the landlord's list line by line. Give every contractor the same documents:
- The reinstatement clause from your lease
- The landlord's written list, or the notes from the joint inspection
- The floor plan or fit-out drawings from when you moved in
- Photos of the unit as you received it, if you have them
- The building's renovation rules and working hours
- Your handover date
Check each quote says
0 of 7 reviewed
Use this to track your review. Checks stay on this page while it is open.
If one quote leaves an item out, it isn't cheaper, it's pricing less of the list. For the approvals a fit-out needed going in, see which approvals a shop or office renovation needs, and the commercial renovation buying guide covers the lease clauses to read before you sign the next one. The hacking buying guide explains how demolition work is priced and planned.
Get the list priced well before your deadline
Send us the reinstatement clause and your landlord's list, and we'll do a free site assessment of the unit. We measure, note what each item needs, and send a fixed-price quote within 3 to 5 working days of the visit, never from a photo.
Our specialist does the removal work, and we supervise it through to handover, walking the unit with you before you hand it back. Where the list touches the fire safety systems or anything that may be structural, we arrange the Qualified Person or engineer.
Common questions
Can the next tenant take over my fit-out instead?
Ask your landlord, and if they agree, get it in writing, naming each item that stays. Anything the written agreement leaves out may still be on your reinstatement list.
How do I know whether a wall in my unit is structural?
Not by looking at it. A non-load bearing wall is one that supports no load other than its own weight, and that's for an engineer and the building's approved plans to settle. Ask your landlord or managing agent for the plans, and have it checked before it's hacked.