- Approved structural plans and a permit to carry out the work are separate documents.
- Ask about the specific work package due to start, particularly on a phased project.
- Have the appointed QP resolve exemption or amendment questions before relying on a contractor’s start date.
Plan approval alone is not the start signal
For structural A&A works that require approval, an approved drawing is not by itself permission to start construction. BCA says a permit must be obtained before the structural works start. Its application involves the developer, appointed Qualified Person and builder. Ask the QP to confirm the status of the work you are about to authorise.
Sources: Building and Construction Authority: Structural Plan submission
Separate these three statements
A contractor may say that the project is “approved” while referring to planning, structural drawings or a permit. The word is too broad to settle a start decision.
Scroll across to compare all columns →
| Statement | What it does not establish | Useful follow-up |
|---|---|---|
| “The proposal is A&A.” | That the structural work is exempt or ready to begin. | Which planning route and building-control requirements apply to this scope? |
| “The structural plans are approved.” | That the necessary permit is in place. | Can the QP identify the permit covering the proposed start? |
| “We can start the next phase.” | That a different phase or changed design is covered. | Which drawings, scope and outstanding conditions apply to that phase? |
Editorial document-checking aid; the QP determines the applicable process.
Check the scope beside the paperwork
Send the team a short description of the next operation, such as the proposed structural opening or extension foundation works. Request confirmation against its drawing references and current design. This is more useful than collecting an approval email without knowing what it covers.
Exemptions and changes require their own assessment. BCA distinguishes insignificant works and material structural changes; a homeowner should not decide that an alteration is exempt merely because it is small. URA’s A&A planning classification is also a separate question.
Sources: Building and Construction Authority: Structural Plan submission · Urban Redevelopment Authority: Additions and Alterations to Landed Housing
Put the confirmation into the programme
Agree that the builder’s programme shows what has to be resolved before each relevant work package starts. If the design changes after a start date was proposed, ask for an updated confirmation and schedule. A booked delivery or paid deposit cannot resolve an outstanding approval question.
Sources and scope
Our editorial team checked the references below. Manufacturer guidance applies to the products and arrangements it describes; confirm the documents for your proposed installation.
- Structural Plan submission
Building and Construction Authority · Checked
Structural-plan applicant qualifications, permit process and additional certification considerations for A&A.
- Additions and Alterations to Landed Housing
Urban Redevelopment Authority · Checked
Planning A&A criteria, additional-storey reconstruction classification and conditional retention of previously approved non-conforming structures.
Related Services
Need Help With Your Project?
Get a free site assessment and no-obligation quote.
About the author
Written by the DirectHome team, Singapore home-upgrade contractors coordinating licensed lift, pool, roofing and gate specialists. We coordinate BCA-permitted works through licensed specialist partners across landed property in Singapore.